By Associated Press - Thursday, April 11, 2019

RALEIGH, N.C. (AP) - The country’s largest electric company says it’s challenging an order by North Carolina’s environmental agency to excavate coal ash from all of its power plant sites in the state.

Duke Energy Corp. said Thursday it will file an administrative appeal by May 1. The order could cut the risk of toxic chemicals leaking into water supplies but add billions of dollars to electricity bills.

The company has said it wants to cover the storage pits at six power plants with a waterproof cap, calling it a cheaper option that would prevent rain from passing through and carrying chemicals through the unlined bottoms.



The Charlotte-based company says complete excavation would cost about $10 billion, nearly double current estimates. Consumer advocates are demanding the company’s shareholders pay that bill instead of customers.

Copyright © 2025 The Washington Times, LLC.

Please read our comment policy before commenting.

PIANO END ARTICLE RECO