By Associated Press - Wednesday, February 21, 2018

NEW CASTLE, Del. (AP) - The rebuild of a Delaware bridge expected to be completed last Thanksgiving after initial delays is now expected to extend into March.

Delaware Department of Transportation spokesman C.R. McLeod told The News Journal of Wilmington on Monday those delays have added an extra $1 million to Del. 141 bridge’s cost. Mumford and Miller Concrete Inc. planned to begin construction last summer, but delays pushed the start date to fall.

The discovery of an asbestos conduit by workers slicing into the old structure delayed plans further. Delaware DOT says the conduit wasn’t included in the company’s $15.6 million design plans, but original bridge blueprints from the 1950s, which the company should have referenced, showed it.



A McCormick Taylor employee said they couldn’t comment Monday as the project designer was unavailable.

___

Information from: The News Journal of Wilmington, Del., http://www.delawareonline.com

Copyright © 2025 The Washington Times, LLC.

Please read our comment policy before commenting.

PIANO END ARTICLE RECO